Add to Cart
Building Material Mixture Machine Maximum Towing Speed 20km/h
The main technical parameters
Model | JZM500 | JZM750 | JZM1000 | |
Output capacity | (L) | 500 | 750 | 1000 |
Feed capacity | (L) | 800 | 1200 | 1200 |
Productivity | (m³/h) | 18-20 | 30-35 | 35-40 |
Mixing barrel speed | (r/min) | 15 | 12.26 | |
Water supply accuracy | error≤2% | error≤2% | error≤2% | |
Stirring motor | (kw) | 2*5.5 | 2.2*7.5 | 2*11 |
Lift motor | (kw) | 5.5 | 7.5 | 7.5 |
water pump motor | (kw) | 1.1 | 1.1 | 1.1 |
Tire specifications | 7-16 | 7.50-16 | 6.50-16 | |
Maximum towing speed | (km/h) | 20 | 20 | 20 |
Dimensions (L* W*H) | (mm) | 3000*2100*2500 | 3900*2200*2900 | 4200*2100*2700 |
Total Weight | (kg) | 1900 | 2400 | 2900 |
Scope of application
|
Use safety
1. The mixer should be set up in a flat position, with square wood
used to cushion the front and rear axles, so that the tires are
elevated to avoid walking during operation.
2. The mixer should be equipped with secondary leakage protection.
After the power is turned on before work, it must be carefully
inspected and deemed qualified after the empty car test run before
use. During the trial operation, it is necessary to check whether
the mixing drum speed is appropriate. Generally, the empty car
speed is slightly faster than the car (after loading) by 2-3
revolutions. If there is a significant difference, the ratio of the
driving wheel to the transmission wheel should be adjusted.
3. The rotation direction of the mixing drum should comply with the
direction indicated by the arrow. If not, the motor wiring should
be corrected.
4. Check whether the transmission clutch and brake are flexible and
reliable, whether the steel wire rope is damaged, whether the track
pulley is in good condition, whether there are obstacles around,
and the lubrication of various parts.
5. After starting up, always pay attention to the normal operation
of all components of the mixer. When shutting down, frequently
check if the mixer blades are bent and if the screws are loose or
loose.
6. When the concrete has been mixed or is expected to stop for more
than 1 hour, in addition to discharging the remaining materials,
stones and clean water should be poured into the shaking drum, and
the machine should be turned on and turned to rinse the mortar
adhered to the drum before unloading it completely. There should be
no accumulated water inside the material barrel to prevent rusting
of the barrel and blades. At the same time, the accumulated ash
outside the mixing drum should also be cleaned to keep the
machinery clean and intact.
7. After work and when not in use during shutdown, the power should
be turned off and the switch box locked to ensure safety.